Multiple Choice
If a company applies overhead to production with a predetermined overhead rate, a credit balance in the Factory Overhead account at the end of the period means that:
A) The overhead was underapplied for the period.
B) Actual overhead was greater than the overhead amount applied to production.
C) The bookkeeper has made an error because the debits don't equal the credits.
D) The balance will be carried forward to the next period as an overhead cost.
E) Actual overhead incurred was less than the overhead amount applied to production.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: If actual overhead incurred during a period
Q9: The amount by which the overhead applied
Q10: KL Company uses a job order costing
Q11: The Marina Corp. has applied overhead
Q12: A _ is a separate record maintained
Q14: In comparison to a general accounting system,
Q15: Calwell Corp. uses a job order
Q16: If overapplied or underapplied overhead is material,
Q17: When a job involves producing more than
Q18: Overapplied overhead is the amount by which