Multiple Choice
When using a standard costing system,which of the following should be recorded for labor as a product is being made?
A) Debit wages payable for the actual hours of labor at the standard rate and credit work in process for the actual hours worked at the standard rate
B) Debit payable wages for the standard hours at the standard rate and credit work in process for the actual hours at the actual rate
C) Credit wages payable for the standard hours at the standard rate and debit work In process for the standard hours at the actual rate
D) Credit wages payable for the actual hours at the actual rate and debit work in process for the standard hours at the standard rate
Correct Answer:

Verified
Correct Answer:
Verified
Q5: What is the difference between a normal
Q6: When using a standard costing system,the direct
Q13: A costing system where direct material and
Q16: When using a standard costing system,recording events
Q17: When using a standard costing system,which of
Q23: When using a standard costing system,direct material
Q26: At what amount will the inventory and
Q31: When using a standard costing system,which of
Q33: When using a standard costing system,which of
Q36: Manufacturing Overhead is a temporary account that