True/False
Three methods used for estimating the fixed and variable portions of a cost include: cost-cover graphs,the high-False - Three methods used for estimating the fixed and variable portions of a cost include scattergraphs,the high-low method and regression analysis.
Correct Answer:

Verified
Correct Answer:
Verified