On January 4th,Stevens Manufacturing received an order for 30 uniforms.The following information pertained to that order. Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00
Calculate the manufacturing cycle efficiency.
A) 70%
B) 60%
C) 69%
D) 10%
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Benchmarking participants should adhere to the Benchmarking
Q32: Which of the following is not a
Q36: For processes that are not identical, companies
Q102: Which of the following is not a
Q149: Traditionally,organizations have evaluated their performance using only
Q150: Earnings per share is a financial measure
Q153: A balanced scorecard should include five to
Q155: The best measures relate to corporate strategy
Q157: The first step in developing a
Q159: From a customer's perspective,the time lapse between