Essay
Patton's Manufacturing has provided the following information relating to a large order of Part #2347 transistors for a major customer:
Raw materials ordered for Part #2347 July 1st
Part #2347 put into production July 12th
Part #2347 completed July 13th
Part #2347 transferred to finished goods July 14th
Date order accepted July 15th
Order assembled July 17th,July 18th,July 19th
Order delivered to warehouse July 21st.
Warehouse packaged order July 23
Call to customer that order was ready July 24th
Customer picked up order July 24th
What is the delivery cycle time?
Appendix,
Correct Answer:

Verified
July 1st thr...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q23: A lagging indicator "lags" the time period
Q30: Measures that help predict a future result
Q47: A balanced scorecard should include five to
Q49: The time from the start of a
Q51: Qualitative indicators<br>A)tend to be based on feelings.<br>B)tend
Q52: Lagging indicators can be used to<br>A)measure past
Q53: Which of the following is a measure
Q53: Midstate Industries is a retail clothing store.Marilyn
Q96: Which of the following is not an
Q123: Which of the following is not an