A Local Engineering Firm Is Bidding on a Design Project

Question 45

Essay

A local engineering firm is bidding on a design project for a new client. The total budgeted direct-labor costs for the firm are $400,000. The total budgeted indirect costs are $600,000. It is estimated that there are 8,000 billable hours in total.
Required:
a. What is the budgeted direct-labor cost rate?
b. What is the budgeted indirect-cost rate assuming direct-labor cost is the allocation base?
c. What should be the engineering firm bid on the project if the direct labor hours are estimated
A local engineering firm is bidding on a design project for a new client. The total budgeted direct-labor costs for the firm are $400,000. The total budgeted indirect costs are $600,000. It is estimated that there are 8,000 billable hours in total. Required: a. What is the budgeted direct-labor cost rate? b. What is the budgeted indirect-cost rate assuming direct-labor cost is the allocation base? c. What should be the engineering firm bid on the project if the direct labor hours are estimated

Correct Answer:

verifed

Verified

a. $400,000/8,000 = $50/hour
b...