Answer the following questions using the information below:
-In a 2-variance analysis the flexible-budget variance and the production-volume variance should be ________, respectively.
A) $11,000 U; $110,000 U
B) $41,000 U; $80,000 U
C) $21,000 U; $100,000 U
D) $121,000 U; Zero