Multiple Choice
To complete the first setup on a new machine took an employee 100 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take:
A) 80 minutes
B) 60 minutes
C) 40 minutes
D) 30 minutes
Correct Answer:

Verified
Correct Answer: