The Product Data Center Has Been Servicing the Struble Production

Question 2

Essay

The Product Data Center has been servicing the Struble Production Casting Department for five years. Beginning next year, the company is adding a Production Molding Department to compliment the materials produced by the Struble Production Casting Department. As a result, data center costs are expected to increase from $700,000 per year to $800,000 per year. The Production Molding Department will use 20% of the data center efforts.
Required:
a. Using the stand-alone cost-allocation method, identify the amount of data center cost that will be allocated to Struble Production Casting and the Production Molding Department next year.
b. Using the incremental cost-allocation method, identify the amount of data center cost that will be allocated to Struble Production Casting and the Production Molding Department next year.