Multiple Choice
Answer the following questions using the information below:
The tool crib at a large manufacturing company is responsible for providing tools to the factory workers on demand. The tool crib has a variable demand. Historically, its demand has ranged from 300 to 500 small tools per day with an average of 400. Diane, the tool crib attendant, works eight hours a day, five days a week. Each order is for one small tool and each small tool takes Diane 1 minute to retrieve from the bins.
-What is the average waiting time, in minutes?
A) 1
B) 1.5
C) 2.5
D) 3.5
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The financial cost of quality measures serves
Q40: Answer the following questions using the information
Q42: The theory of constraints considers a short-run
Q43: The number of design and process changes
Q46: Two common operational measures of time are
Q47: A Pareto Diagram is usually in a
Q49: An example of a nonfinancial measure for
Q60: Discuss the means by which a company
Q119: A liability claim is an example of
Q126: Answer the following questions using the information