Multiple Choice
Vestor Ltd.has estimated a 90% cumulative average-time learning curve applies to labour time to manufacture its new product.The first unit took 18 hours.If Vestor's estimates are correct, how many hours will be used to manufacture 4 total units?
A) 14.58 hours
B) 64.80 hours
C) 72.00 hours
D) 64.01 hours
E) 58.32 hours
Correct Answer:

Verified
Correct Answer:
Verified