The Demand for Ballard's Glass Company's Products Varies

Question 76

Multiple Choice

The demand for Ballard's Glass Company's products varies.Each order is one window, and each window takes 26 minutes to install.Assuming wait time is 12 minutes, and order receipt time equals 21 minutes what is the cycle time for an order on average?


A) 21 minutes
B) 26 minutes
C) 38 minutes
D) 41 minutes
E) 59 minutes