Multiple Choice
Quick Shop Printing has two workstations, cutting and pasting. The cutting station is limited by the speed of operating the cutting machine. Pasting is limited by the speed of the workers. Pasting normally waits on work from cutting. Each department works an eight-hour day. If cutting begins work two hours earlier than pasting each day, the two departments generally finish their work at about the same time. Not only does this eliminate the bottleneck, but it increases finished units produced each day by 80 units. All units produced can be sold. The cost of operating the cutting department two more hours each day is $800. The contribution margin of the finished products is $3 each. Inventory carrying costs are $0.20 per unit per day. What is the daily capacity of the pasting workstation?
A) 320
B) 400
C) 440
D) 800
E) 820
Correct Answer:

Verified
Correct Answer:
Verified
Q29: Baby Care Products has just completed a
Q48: In the banking industry, depositing a customer's
Q69: Cari and Jereme just bought a bed
Q84: Costs of quality (COQ)reports usually do not
Q127: The annual capacity of a machine is
Q130: The operational measures of time reveal how
Q136: Which of the following are typically not
Q137: How much will internal failure costs change
Q138: In the incremental unit-time learning model, the
Q152: Costs of quality include all of the