Multiple Choice
Welch Company budgeted the following cost standards for the current year: Direct materials = 1.40 kilos per unit @ $1.50 per kilo
Direct labor = 0.75 hours per unit @ $6 per hour
Actual production and costs were as follows:
Units produced = 2,800
Direct materials used = 4,500 kg.
Direct materials purchased = 5,000 kg. @ a cost of $5,850
Direct labor incurred = 2,000 hours at a cost of $13,000
The material efficiency variance was
A) $1,650 F
B) $870 U
C) $2,520 U
D) $780 F
Correct Answer:

Verified
Correct Answer:
Verified
Q11: A standard cost variance is the difference
Q80: Everett Ltd budgeted $1,488,000 for total overhead.
Q81: A variance that is considered immaterial should
Q82: In a traditional manufacturing accounting system, the
Q83: The process of calculating variances and analysing
Q86: Hogle Manufacturing uses a standard costing system.
Q88: Hyteck Ltd is a capital intensive firm.
Q89: During the period Richeleau produced 1,000 units
Q90: The production volume variance provides information about<br>A)
Q100: Expected costs per unit of input are