Given the Following Account Balances at the End of the First

Question 96

Multiple Choice

Given the following account balances at the end of the first year of operations: Given the following account balances at the end of the first year of operations:   Assuming that variances are considered material, the entry and amount of the direct material efficiency variance allocated to work in process inventory is A)  Credit $26,000 B)  Credit $24,375 C)  Debit $17,333 D)  Debit $8,125 Assuming that variances are considered material, the entry and amount of the direct material efficiency variance allocated to work in process inventory is


A) Credit $26,000
B) Credit $24,375
C) Debit $17,333
D) Debit $8,125