Multiple Choice
Everett Ltd budgeted $1,488,000 for total overhead. The standard variable overhead rate was $2 per direct labor hour, or $6 per unit, based on an anticipated activity level of 600,000 direct labor hours. During the year 220,000 units were produced. Fixed overhead costs incurred were $300,000. The variable overhead budget variance was $19,800 unfavorable, and the actual variable overhead rate was $2.10 per direct labor hour. The actual variable overhead costs incurred were
A) $1,339,800
B) $1,320,000
C) $1,260,000
D) $1,300,200
Correct Answer:

Verified
Correct Answer:
Verified
Q23: The production manager of CLR calculated a
Q24: A contract with a new supplier may
Q25: During the period Richeleau produced 1,000 units
Q27: During the period Richeleau produced 1,000 units
Q29: Because managers use estimates in calculating overhead
Q30: Rewarding employees in one production department for
Q32: Hogle Manufacturing uses a standard costing system.
Q33: Everett Ltd budgeted $1,488,000 for total overhead.
Q91: Variance analysis involves the steps listed below.
Q109: The total standard cost for a unit