Multiple Choice
Everett Ltd budgeted $1,488,000 for total overhead. The standard variable overhead rate was $2 per direct labor hour, or $6 per unit, based on an anticipated activity level of 600,000 direct labor hours. During the year 220,000 units were produced. Fixed overhead costs incurred were $300,000. The variable overhead budget variance was $19,800 unfavorable, and the actual variable overhead rate was $2.10 per direct labor hour. The variable overhead efficiency variance was
A) $76,000 U
B) $63,800 U
C) $46,200 F
D) $44,000 F
Correct Answer:

Verified
Correct Answer:
Verified
Q18: Mason Ltd uses a standard costing system.
Q19: Pardee Ltd completed operations for the week
Q22: At the end of 2010, ELM's production
Q23: The production manager of CLR calculated a
Q24: A contract with a new supplier may
Q25: During the period Richeleau produced 1,000 units
Q28: The direct materials price variance is often
Q43: If a variance is considered material, it
Q85: If a variance analysis shows that operations
Q109: The total standard cost for a unit