Multiple Choice
When calculating the budgeted rate for direct professional time,the numerator is:
A) budgeted number of professional hours.
B) actual number of professional hours.
C) budgeted cost of professional time.
D) actual cost of professional time.
Correct Answer:

Verified
Correct Answer: