A local engineering firm is bidding on a design project for a new client.The total budgeted direct-labour costs for the firm are $800 000.The total budgeted indirect costs are $1 200 000.It is estimated that there are 16 000 billable hours in total.
Required:
a.What is the budgeted direct-labour cost rate?
b.What is the budgeted indirect-cost rate assuming direct-labour cost is the allocation base?
c.If the firm has a 20% mark-up percentage,what should it bid on the project if the direct labour hours are estimated at 500 hours?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Correct Answer:

Verified
a.$800 000/16 000 = $50/hour
b...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
b...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q85: When management accountants use process-costing systems,they separate
Q86: Degree of variation captures the extent to
Q87: What does over-costed output lead to?<br>_<br>_
Q88: Direct costs of a cost object are
Q89: The shorter the period used to calculate
Q91: Actual costing is a costing system that
Q92: Schmenner classifies services into four categories-professional service,service
Q93: The actual cost-driver rate measures _ capacity
Q94: To motivate people to make decisions and
Q95: What type of costs is related to