Solved

Answer the Following Questions Using the Information Below

Question 139

Multiple Choice

Answer the following questions using the information below:
Tiger O'Reilly planned to use $85 of material per unit but actually used $82 of material per unit,and planned to make 1200 units but actually made 1000 units.
-The flexible-budget variance is:


A) $3000 favourable.
B) $2400 favourable.
C) $14 000 unfavourable.
D) $16 400 unfavourable.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge