Multiple Choice
A flexible-budget variance is $800 favourable for unit-related costs.This indicates that costs were:
A) $800 less than the standard for the achieved level of activity.
B) $800 more than the standard for the achieved level of activity.
C) $800 more than the master budget.
D) $800 less than for the planned level of activity.
Correct Answer:

Verified
Correct Answer:
Verified