Answer the Following Questions Using the Information Below:
Shepparton Water

Question 2

Multiple Choice

Answer the following questions using the information below:
Shepparton Water Sports has prepared the following flexible budget for September and is in the process of interpreting the variances.F denotes a favourable variance and U denotes an unfavourable variance.
 Flexible  Variances  Budget  Price  Efficlency  Material A $20000$1000 F$3000U Material B 30000500U1500 F Direct mantufacturing labour 40000500U2500 F\begin{array} { l r r r } & \text { Flexible } & { \text { Variances } } \\& \underline { \text { Budget } } & \text { Price } & \text { Efficlency } \\\text { Material A } & \$ 20000 & \$ 1000 \mathrm {~F} & \$ 3000 \mathrm { U } \\\text { Material B } & 30000 & 500 \mathrm { U } & 1500 \mathrm {~F} \\\text { Direct mantufacturing labour } & 40000 & 500 \mathrm { U } & 2500 \mathrm {~F}\end{array}
-The actual amount spent for direct manufacturing labour was:


A) $42 000.
B) $43 000.
C) $40 000.
D) $38 000.

Correct Answer: