Multiple Choice
If Freemantle Ferry Company has a safety stock of 240 units and the average daily demand is 30 units,how many days can be covered if the shipment from the supplier is delayed by 12 days?
A) 12.0 days
B) 6.7 days
C) 8.0 days
D) 10.0 days
Correct Answer:

Verified
Correct Answer:
Verified