Multiple Choice
If Activity C directly precedes both D and E on a project network, and C can be crashed three (3) times using linear programming, then:
A) crash time affects only C.
B) crash time affects only C and D.
C) crash time affects only C and E.
D) crash time affects both D and E.
Correct Answer:

Verified
Correct Answer:
Verified