Solved

If Activity C Directly Precedes Both D and E on a Project

Question 16

Multiple Choice

If Activity C directly precedes both D and E on a project network, and C can be crashed three (3) times using linear programming, then:


A) crash time affects only C.
B) crash time affects only C and D.
C) crash time affects only C and E.
D) crash time affects both D and E.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge