Steve, an Operations Manager at Krypto InfoTech, Must Set Up

Question 8

Multiple Choice

Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate) is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations.
SHAPE \* MERGEFORMAT
 Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -What is the cycle time? A)  6 minutes/unit B)  7 minutes/unit C)  8 minutes/unit D)  9 minutes/unit  Steve, an operations manager at Krypto InfoTech, must set up an assembly line to assemble a computer mouse. The precedent network given below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast (output rate)  is 60 units per shift. He decides to use the longest/largest-task-time rule to assign tasks to workstations. SHAPE \* MERGEFORMAT      Worksheet for assembly-line balancing problem   \begin{array}{|c|c|c|c|} \hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\ \hline \text { A } & & & \\ \hline \text { B } & & & \\ \hline \text { C } & & & \\ \hline \text { D } & & & \\ \hline \text { E } & & & \\ \hline \text { F } & & & \\ \hline \end{array}  Use the previous assembly-line balancing (ALB)  information to answer Questions . -What is the cycle time? A)  6 minutes/unit B)  7 minutes/unit C)  8 minutes/unit D)  9 minutes/unit Worksheet for assembly-line balancing problem
 Workstation  Assigned Tasks  Total Time  Idle Time  A  B  C  D  E  F \begin{array}{|c|c|c|c|}\hline \text { Workstation } & \text { Assigned Tasks } & \text { Total Time } & \text { Idle Time } \\\hline \text { A } & & & \\\hline \text { B } & & & \\\hline \text { C } & & & \\\hline \text { D } & & & \\\hline \text { E } & & & \\\hline \text { F } & & & \\\hline\end{array} Use the previous assembly-line balancing (ALB) information to answer Questions .
-What is the cycle time?


A) 6 minutes/unit
B) 7 minutes/unit
C) 8 minutes/unit
D) 9 minutes/unit

Correct Answer: