Multiple Choice
Assembly-Line Balancing Problem-Table 1 below
The Florida Appliance Company is installing an assembly line to produce vacuum cleaners, and Patrick, as an operations manager, is responsible for balancing the line. The work elements to be performed are listed, along with their items and immediate predecessors.
-Use the information in Table 1. The company is planning to operate 2 shifts per day, 8 hours per shift. If the desired output rate of the line is 480 units per day, what is the cycle time?
A) 60 seconds
B) 120 seconds
C) 180 seconds
D) 240 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q18: The twelve tasks necessary to assemble
Q19: Describe approaches used for process layout design.
Q20: The eleven tasks necessary to assemble
Q21: Explain the sociotechnical approach to job design
Q22: Product layouts are less flexible than process
Q24: For the following assembly-line data, balance
Q25: The predominant layout type used in hospitals
Q26: _ layout is used for high volumes
Q27: _ is the horizontal expansion of a
Q28: An assembly line with 28 activities is