Multiple Choice
The eleven tasks defined in Table 1 given below are necessary to assemble an MP3 player along with their time (in seconds) and flow diagram,
Table 1
-Refer to Table 1. Using this data and a cycle time of 60 seconds, determine an assembly-line balance by using the longest-task-time rule.
A) Station 1: A, B
Station 2: C, D
Station 3: E, F
Station 4: G, H
Station 5: J, I, K
B) Station 1: A, B
Station 2: C, D
Station 3: E, F
Station 4: G, H
Station 5: J
Station 6: I, K
C) Station 1: A, B
Station 2: C, E
Station 3: D, F
Station 4: G
Station 5: H, I
Station 6: J, K
D) Station 1: A, B
Station 2: C, D
Station 3: E, F
Station 4: G
Station 5: H, J
Station 6: I, K
Correct Answer:

Verified
Correct Answer:
Verified
Q80: The nine tasks necessary to assemble
Q81: In a process layout technique, improvement is
Q82: A(n) _ team performs entire jobs rather
Q83: A company is setting up an
Q84: A fixed-position layout is based on the
Q86: In a perfectly balanced assembly line, no
Q87: Consider the following assembly line information
Q88: The determination of specific job tasks and
Q89: The volume of demand in product layout
Q90: Which of the following is NOT a