Multiple Choice
In the disaggregation framework, the direct inputs to material requirements planning (MRP) include all of the following EXCEPT:
A) master production schedule (MPS) .
B) transaction files.
C) bills of materials (BOM) .
D) capacity requirements plan (CRP) .
Correct Answer:

Verified
Correct Answer:
Verified