Multiple Choice
If a work center load report indicates insufficient capacity, options for correcting the problem include all of the following EXCEPT:
A) revising the bill of materials.
B) changing the master product schedule.
C) subcontracting.
D) transferring personnel between work centers.
Correct Answer:

Verified
Correct Answer:
Verified