A sheet metal company has developed the following six-month production schedule (in thousands of square yards):
 Week 123456 Metal 150100175200160160\begin{array} { | l | l | l | l | l | l | l | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Metal } & 150 & 100 & 175 & 200 & 160 & 160 \\\hline\end{array} In addition, their monthly labor and machine capacities (in hours) available, and the production standards (in hours per square yard) are:
 Labor  Machine  Capacity Available 16,00020,000 Production Standard .10.18\begin{array}{|l|l|l|}\hline & \text { Labor } & \text { Machine } \\\hline \text { Capacity Available } & 16,000 & 20,000 \\\hline \text { Production Standard } & .10 & .18 \\\hline\end{array}
a.What is the percentage utilization of the labor capacity in month 4?
b.What is the percentage utilization of the machine capacity in month 3?
c.In which weeks are the labor requirements over capacity?

Correct Answer:

verifed

Verified

a. 125.0; ...