The table below includes processing times and due dates for five jobs.
 Processing  Days Due  Job  Time (days)   From Today  A 1624 B 2330 C 2240 D 828 E 1018\begin{array}{|l|l|l|}\hline & \text { Processing } & \text { Days Due } \\\hline \text { Job } & \text { Time (days) } & \text { From Today } \\\hline \text { A } & 16 & 24 \\\hline \text { B } & 23 & 30 \\\hline \text { C } & 22 & 40 \\\hline \text { D } & 8 & 28 \\\hline \text { E } & 10 & 18 \\\hline\end{array}
-Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.


A) more than 10 but less than or equal to 20 days
B) more than 20 but less than or equal to 30 days
C) more than 30 but less than or equal to 40 days
D) more than 40 days