Multiple Choice
The sequencing rule that minimizes the maximum number of jobs that are past due from a given set of jobs is:
A) shortest processing time (SPT) .
B) earliest due date (EDD) .
C) first come, first served (FCFS) .
D) least amount of work at the next process queue (LWNQ) .
Correct Answer:

Verified
Correct Answer:
Verified