A print shop has five large commercial printing jobs to finish. They are trying to decide whether to use the shortest processing time (SPT) or the first come, first served (FCFS) sequencing rule. Data on estimated processing time (in hours) and time to promised completion (in hours) is as follows (jobs shown in order of arrival):
a.What is the average flow time in hours using the FCFS rule?
b.What is the average job lateness in hours using the FCFS rule?
c.What is the average flow time in hours using the SPT rule?
d.What is the average job lateness in hours using the SPT rule?
Correct Answer:

Verified
a.First come, first served (FCFS):
Order...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Order...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q26: The following five jobs, along with
Q27: High flow times reduce work-in-process (WIP) inventory.
Q28: The following five jobs, along with
Q29: ScheduleAnywhere.com, an online software, helps clients do
Q30: What are the four steps involved in
Q32: Appointments can be viewed as a reservation
Q33: Triage by nurses in an emergency room
Q34: In sequencing jobs in a flow shop
Q35: Rescheduling rarely occurs unless customers change their
Q36: Short-term capacity fluctuations necessitate changes in schedules.