You Are Responsible for Managing an Advertising Project with the Following
Question 52
Question 52
Multiple Choice
You are responsible for managing an advertising project with the following activities (times are given in weeks) . Activity A B C D E F G Immediate Predecessor none none none A, B C A D. E F Normal Time (Weeks) 3625274 Crash Time (Weeks) 2613163 Normal Cost ($) $14,000$5,500$6,000$7,500$9,000$15,000$8,400 Crash Cost ($) $16,500$5,500$8,000$14,500$10,500$18,000$10,000 Draw the project network here. BLANK SPACES -The project completion time is _____.
A) 12 weeks B) 13 weeks C) 14 weeks D) 15 weeks