Essay
The Huyden Company builds equipment to customer's specifications. On March 1, two jobs were in process with the following costs and information:
*Applied on the basis of machine hours
During March, Job 45 was started and Job 44 was completed and delivered to the customer. Job 43 was missing a part that was backordered and would be completed in June. The following costs were incurred in March:
It is Huyden's policy to bill clients at cost plus 40 percent.
Required:
a.
Calculate the overhead rate that Huyden is using.
b.
Calculate the overhead applied to each job during the month of March.
c.
Calculate the balance in work in process on March 31.
d.
What was the price of Job 44?
Correct Answer:

Verified
Correct Answer:
Verified
Q11: A(n) _ is a collection of overhead
Q12: Figure 1<br>Harrison Co. produces two products, AB
Q13: Manchester Ltd. uses a job-order costing system
Q15: Figure 1<br>Harrison Co. produces two products, AB
Q17: The following information pertains to Utter Company:
Q18: Figure 3<br>Ray Manufacturing has four categories of
Q19: Walter Company uses a job-order costing system
Q20: Newton Company has two support departments, Maintenance
Q21: Which of the following methods of assigning
Q21: A department that is capital-intensive most likely