Multiple Choice
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity cost drivers for each activity have been identified and their practical capacities listed: The costs of facility-level activities are assigned using machine hours.
What is(are) the product-level activity(ies) ?
A) engineering
B) setups
C) inspecting
D) none of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Owens Ltd. produces specially machined parts. The
Q5: An activity-based cost system<br>A)differs from a traditional-based
Q8: Funk Manufacturing Company produces specially machined parts.
Q9: Figure 5<br>Peach, SA., has identified the following
Q10: Ubben Manufacturing uses an activity-based costing system.
Q12: Figure 2<br>The management of Chott Industries predicted
Q26: Batch-related costs are added to which of
Q27: If activity-based costing is used, modifications made
Q27: If activity-based costing is used, electricity usage
Q56: Which of the following quantities is an