Multiple Choice
Figure 3
The Overdale plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:
The plant currently applies overhead using direct labour hours and expected capacity of 80,000 direct labour hours. The following data has been assembled for use in developing a bid for a proposed job:
Total expected machine hours for all jobs during the year are 40,000, and the total expected number of inspections is 2,500.
-Refer to Figure 3 above. Using activity-based costing and the appropriate cost drivers, the total cost of the potential job would be
A) £9,230
B) £8,180
C) £2,250
D) £1,680
Correct Answer:

Verified
Correct Answer:
Verified
Q15: What is the initial step in implementing
Q34: The activity-based resource usage model improves managerial
Q43: Compare and contrast traditional organization-based costing with
Q57: Briefly discuss the problem with the unit-level
Q79: Figure 3<br>The Overdale plant has two categories
Q80: The Greenbriar plant has two categories of
Q81: What is cross-subsidization and when is it
Q85: Figure 1 A company usually processes 20,000
Q87: Ernest, SA., has identified the following overhead
Q89: Zipp Company manufactures two products (X and