Armati, SA

Question 38

Multiple Choice

Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data:
The following actually occurred:
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data: The following actually occurred:   The static budget variance for direct materials is   A)  £100 F. B)  £100 U. C)  £400 F. D)  £400 U. The static budget variance for direct materials is
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data: The following actually occurred:   The static budget variance for direct materials is   A)  £100 F. B)  £100 U. C)  £400 F. D)  £400 U.


A) £100 F.
B) £100 U.
C) £400 F.
D) £400 U.

Correct Answer:

verifed