Multiple Choice
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data:
The following actually occurred: The static budget variance for direct materials is
A) £100 F.
B) £100 U.
C) £400 F.
D) £400 U.
Correct Answer:

Verified