Multiple Choice
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data:
The following actually occurred: The static budget for total variable costs is
A) £90 U.
B) £180 U.
C) £790 F.
D) £880 F.
Correct Answer:

Verified
Correct Answer:
Verified