Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data:
The following actually occurred: The flexible budget for direct materials cost in 2004 is
A) £3,500.
B) £3,600.
C) £3,900.
D) £4,000.