Multiple Choice
Armati, SA., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below: Armati, SA., had the following budgeted data:
The following actually occurred: The flexible budget variance for total cost for 2004 is
A) £90 U.
B) £140 U.
C) £230 U.
D) £50 U.
Correct Answer:

Verified
Correct Answer:
Verified