The materials price variance is calculated as
A) (Actual price - Standard price) x Actual quantity
B) (Actual price - Standard price) x Standard quantity
C) (Actual quantity - Standard quantity) x Actual price
D) (Actual quantity - Standard quantity) x Standard price