Multiple Choice
The labour rate variance is calculated as
A) (Actual hourly wage rate - Standard hourly wage rate) x Actual direct labour hours used
B) (Actual hourly wage rate - Standard hourly wage rate) x Standard direct labour hours that should have been used
C) (Actual direct labour hours used - Standard direct labour hours that should have been used) x Actual hourly wage rate
D) (Actual direct labour hours used - Standard direct labour hours that should have been used) x Standard hourly wage rate
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Variances indicate<br>A)the cause of the variance.<br>B)who is
Q47: Figure 8<br>The following information was extracted from
Q48: Franklin Company expected sales were 2,000 units
Q49: Figure 1<br>Max Company has developed the following
Q51: Figure 5<br>Ebola Company has developed the following
Q53: Which department is usually held responsible for
Q54: Wade Company has developed the following standards
Q55: Standard costs include the quantity and price
Q56: The following standard costs were developed for
Q64: Using more highly skilled direct labourers might