Multiple Choice
Figure 4
Shannon Ltd.'s standard cost card contained the following information:
Direct labour: 1.25 hours x £8.00 per hour = £10.00
Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours.
-Refer to Figure 4. If Shannon's actual labour cost was £136,500, Shannon's labour rate variance was
A) £32,500 unfavorable
B) £32,500 favorable
C) £6,500 unfavorable
D) £6,500 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q4: The materials usage variance is calculated as<br>A)
Q5: During May, 6,000 pounds of raw materials
Q6: Vernon Manufacturing has developed the following standards
Q8: Figure 2<br>Rax Company has developed the following
Q9: If a company was concerned with controlling
Q10: Fosse Manufacturing Company has developed the following
Q11: Figure 7<br>Orient Company has developed the following
Q12: The two variances for variable overhead are<br>A)
Q24: Price variances focus on the difference between<br>A)actual
Q32: The purchase of inferior direct materials at