Multiple Choice
Setup time for a product is 12 hours. A firm that uses JIT and produces the same product has reduced setup time by 1 hour. Setup labour is £20 per hour. If the company wants to reduce nonvalue-added costs by 40 percent next year, the currently attainable standard for setup time would be
A) 7.6 hours.
B) 7.2 hours.
C) 6.6 hours.
D) 4.8 hours.
Correct Answer:

Verified
Correct Answer:
Verified