Multiple Choice
Answer the following questions using the information below:
Munoz, Inc., produces a special line of plastic toy racing cars. Munoz, Inc., produces the cars in batches. To manufacture a batch of the cars, Munoz, Inc., must set up the machines and molds. Setup costs are batch-level costs because they are associated with batches rather than individual units of products. A separate Setup Department is responsible for setting up machines and molds for different styles of car.
Setup overhead costs consist of some costs that are variable and some costs that are fixed with respect to the number of setup-hours. The following information pertains to June 2015:
-Calculate the spending variance for fixed setup overhead costs.
A) $3,200 unfavorable
B) $2,025 unfavorable
C) $3,600 unfavorable
D) $2,025 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q62: Which of the following statements is true
Q63: Answer the following questions using the information
Q64: Use the following information to answer
Q65: Under standard costing,fixed overhead costs are treated
Q66: Use the following information to answer
Q69: Answer the following questions using the
Q71: Answer the following questions using the
Q72: Green Energy Inc.produces fertilizer and distributes
Q155: Neon Company manufactured 2,500 units during April
Q167: Managers can always view a favorable variable