Multiple Choice
Which of the following is a disadvantage of using the standards developed by a firm itself to develop a budget?
A) A firm's inefficiencies will be part of the data.
B) They are not based on realized benchmarks.
C) The expected future changes are not included in the standards.
D) The flexible-budget amounts are difficult to determine.