    Zenich Corp Manufactures Laptops
Solved

Zenich Corp Manufactures Laptops

Question 105

Question 105

Multiple Choice

Zenich Corp manufactures laptops.The waiting time is 60 minutes before the start of production and the manufacturing lead time is 150 minutes per laptop.What is its manufacturing cycle efficiency?


A) 40%
B) 70%
C) 60%
D) 66.67%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33: Costs of Quality (COQ) are classified into

Q63: What are control charts and how can

Q79: Which of the following is considered a

Q100: Answer the following questions using the information

Q102: Answer the following questions using the information

Q104: Six Sigma emphasizes incremental rather than dramatic

Q108: An important difference between financial measures of

Q109: Manufacturing cycle time is _.<br>A) the amount

Q134: A quality improvement program is very costly

Q150: Which of the following is an opportunity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines