Multiple Choice
Answer the following questions using the information below:
Ventaz Corp has a variable demand. Historically, its demand has ranged from 30 to 50 windows per day with an average of 40. Alex works eight hours a day, five days a week. Each order is one window and each window takes 11 minutes.
-What is the average waiting time in minutes?
A) 12.00
B) 55.50
C) 60.50
D) 20.00