Solved

Answer the Following Questions Using the Information Below

Question 74

Multiple Choice

Answer the following questions using the information below:
Ventaz Corp has a variable demand. Historically, its demand has ranged from 30 to 50 windows per day with an average of 40. Alex works eight hours a day, five days a week. Each order is one window and each window takes 11 minutes.
-Alex plans to add doors to its product line and anticipates that they will average 3 doors per day.Each door takes 10 minutes to install. What is the average waiting time,in minutes,if Alex continues to be the only worker?


A) 237.0 minutes
B) 337.0 minutes
C) 257.0 minutes
D) 720.0 minutes

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions